Installation of 300 psf sidewalk shed as per plans. all equipment shall comply with chapter #33 of the 2022 code. no change in use, egress or occupancy under this application.
Provide mechanical work including vrf heating and cooling systems, building ventilation systems. install mechanical exhaust hood work for commercial kitchen of eating and drinking establish. no change...
FACADE INSPECTION Designated Primary Site supervisor: Jesus Decola
Install new plumbing fixtures as per plan. there is no change of use, egress, or occupancy filed under this plan
2026 Auto Show @ JJC - Nissan - Install a temporary exhibit within an existing exhibition building scheduled April 3rd-April 12th, 2026. No change of use, egress or occupancy under this application.
Temporary structure for an WNBA event at HY Plaza. Removed at the end of the programing. No changes to existing structures, use or egress.
Installation of non-emergency gas fired generator with related gas booster pump on existing equipment platform on roof. All work in compliance with TPPN 5/98. No change to occupancy, use, or egress.
Installation of new partitions for gas piping installation as per plans. Installation of new partitions and door with damper on 1st floor. No change to occupancy, use, or egress.
Perform selective removal work, provide new HVAC equip & assoc ductwork, piping, controls, accessories, etc. Protect & reuse existing equipment as shown on plans. Application filed in conjunction with...
2026 Auto Show @ JJC - Stellantis - Install a temporary exhibit within an existing exhibition building scheduled April 3rd-April 12th, 2026. No change of use, egress or occupancy under this applicatio...
Proposed installation of a temporary sidewalk shed as per plans submitted. work shall comply with 2022 building codes, chapter 33. no change in use, egress, or occupancy.
Removal of sprinkler heads and installation of temporary sprinkler loop on the 15th and 16th floor as indicated on drawings.
Plumbing changes on the 7th, 8th and 9th floors as indicated on drawings.
Proposed installation of temporary pipe scaffold as per plans. work shall comply with chapter #33 of 2022 the nyc building code. no change in use, occupancy, or egress under this application.
Installation of temporary suspended scaffolds per plan submitted. work shall comply with 2022 building code chapter 33. no change in use, egress and/or occupancy with this application.
Plumbing modification to existing system and alteration for new tenant fit-out
modification to an existing Sprinkler system to match new space tenants fit out
Installation of temporary suspended scaffolds per plan submitted. work shall comply with 2022 building code chapter 33. no change in use, egress and/or occupancy with this application.
Application for the installation and use of mini-crane as per plans filed herein. No change in egress, use, or occupancy.