Building Permits in ZIP 10016
Manhattan, NY — 488 permits filed recently
488 permits
Debris chute will be installed/built to lower debris from floor to floor. Mechanical means will assist with demolition from exterior and placed on grade.
Install fire sprinkler system as per plans.
Suspended Scaffold for Facade Restoration as Shown on Plans
Installation of knee bracket as per plans. no change in use occupancy or egress under this application.
Removal of existing sprinkler head and installation of temp loop as per plans filed herewith. No change in use, egress or occupancy under this application .
installation of construction fence to protect site
Filing for selective Demolition/Construction and protection related to a Mechanical Equipment upgrade and Structural steel to support ducts to concrete slab.
Application filed for add new gas equipment in a exist. restaurant. plumbing work is filed in conjunction with #m01106366
Tisch Hospital - Limited mechanical alterations to restroom and shower areas on the 7th, 16th, and 17th floors, including exhaust and air distribution modifications. No change to use, occupancy, or eg...
Msb cellar - modifications to an existing sprinkler system as per plans filed herewith. no change in use, egress, or occupancy.
TO REMOVE EXISTING SPRINKLER SYSTEM TOTAL OF 91 SPRINKLER HEADS AND INSTALL NEW TEMPORARY SPRINKLER SYSTEM WITH 65 UPRIGHT SPRINKLER HEADS. AS PER DRAWINGS FILED HERE WITHIN. PROJECT IN CONJUCTION WIT...
Interior renovation of existing eating and drinking establishment on the basement and first floor as per CO 120819061. No changes to use, egress or occupancy.
Interior alterations to apt 8fg. no changes in occupancy use or egress proopsed undere this application.
Herewith filing sprinkler modifications for NYU Langone HCC- Cath Lab Equipment HCC14 Project. No change in use, egress, or occupancy.
Temporary pipe scaffold as per drawings. scaffold shall comply with ch #33 of the nyc bc. no change in use, occupancy or egress under this application.
Filing for selective Demolition/Construction and protection of Partial Cellar through 10th floor related to a Mechanical Equipment upgrade.
Floor 1 : interior renovation of existing lobby. cellar: interior renovation of fitness, corridor & bathrooms. change in use. no egress or occupancy change.
Installation of temporary shoring for the sub-cellar and cellar. no change in use, egress, or occupancy.
FISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decola
STRUCTURAL JOB SCOPE - Opening in existing floor concrete drape mesh for convenience stair and suspended LULA elevator pit.