Preparation Work for Full Demolition - Removal of Glass Windows
Preparation Work for Full Demolition - Removal of Glass Windows
Preparation Work for Full Demolition - Demolition of West Facade for Abatement Access
Interior demolition of non load bearing partitions on the 21st floor (SW corner, former EyeBio) as indicated on drawings
Interior demolition of non load bearing partitions on the 21st floor (SW corner, former EyeBio) as indicated on drawings
Interior demolition of non load bearing partitions on the 21st floor (southside-former Lock8) as indicated on drawings.
Interior demolition of non load bearing partitions on the 21st floor (southside-former Lock8) as indicated on drawings.
Interior demolition of non load bearing partitions on the 27th floor (former Orchestrade ) as indicated on drawings.
Interior demolition of non load bearing partitions on the 27th floor (former Orchestrade ) as indicated on drawings.
Interior demolition of non load bearing partitions on the 15th floor (NE corner) as indicated on drawings.
Interior demolition of non load bearing partitions on the 10th floor (part of northside suite) as indicated on drawings.
Interior demolition of non load bearing partitions on the 15th floor (NE corner) as indicated on drawings.
Interior demolition of non load bearing partitions on the 10th floor (part of northside suite) as indicated on drawings.
Partial Demolition of East Facade to create access opening for construction hoist
Engineered Enclosure System on Scaffolding for Full Building Demolition
Partial Demolition of East Facade to create access opening for construction hoist
Engineered Enclosure System on Scaffolding for Full Building Demolition
Preparation Work for Full Building Demolition - Interior Demolition
Preparation Work for Full Building Demolition - Interior Demolition
Installation of shoring for truck corridor