Permits (88)
Dyckman houses, installation of temporary boiler stacks, steam, condensate, make-up water piping connected to existing heating plant to provide heat during the heating season in conjunction with dob #...
Dyckman houses (building #8), installation of 560 linear feet of 8 feet high construction fence in conjunction with dob # m00636179, m00636184, m00636494, m00688340, m00691924, m00692472 to secure the...
NYCHA Boilers: Dyckman Building 5: Mechanical work associated with Boiler replacement as per plans filed herewith.
NYCHA BOILERS Dyckman: Building 5: Site/Civil work in relation to boiler replacement as per plans filed herewith
NYCHA BOILER -Dyckman: Building 5.Structural work in relation to boiler replacement as per plans filed herewith. Concrete pads, Post installed anchors and support for new Flues and Boilers
NYCHA Boilers Dyckman: Building 3: Site/Civil work as per plans filed herewith. No change to use, egress or occupancy.
NYCHA BOILERS Dyckman: Building 5: Site/Civil work in relation to boiler replacement as per plans filed herewith
Dyckman houses, installation of temporary boiler stacks, steam, condensate, make-up water piping connected to existing heating plant to provide heat during the heating season in conjunction with dob #...
NYCHA Boilers: Dyckman Building 5: Mechanical work associated with Boiler replacement as per plans filed herewith.
NYCHA Boilers Dyckman: Building 3: Site/Civil work as per plans filed herewith. No change to use, egress or occupancy.
Dyckman houses (building #8), installation of 560 linear feet of 8 feet high construction fence in conjunction with dob # m00636179, m00636184, m00636494, m00688340, m00691924, m00692472 to secure the...
NYCHA BOILER -Dyckman. Building 8: Structural work in relation to boiler replacement as per plans filed herewith. Concrete pads, Post installed anchors and support for new Flues and Boilers
NYCHA Boiler Dyckman: Building 8 Mechanical work in association with boiler replacement as per plans filed herewith.
NYCHA BOILER -Dyckman: Building 3. Structural work in relation to boiler replacement as per plans filed herewith. Concrete pads, Post installed anchors and support for new Flue.
NYCHA BOILER -Dyckman: Building 1. Civil/Site work in relation to boiler replacement as per plans filed herewith
NYCHA Boilers Dyckman: Building8; General Construction associated with boiler replacement as per plans filed herewith.
NYCHA Boiler: Dyckman: Building 4: Architectural work to include Sealant, firestopping, patching, wall repairs in relation to Boiler replacement as per plans filed herewith
NYCHA Boilers: Dyckman: Building Building4: Mechanical work associated with boiler replacement as per plans filed herewith.
NYCHA Boilers: Dyckman: Building 6: General Construction in relation to boiler replacement as per plans filed herewith. No change to use, egress or occupancy.
NYCHA Boilers: Dyckman: Building 1: Mechanical work in relation to boiler replacement as per plans filed herewith. Replacing exhaust fan and adding a steam unit heater